Report for September
- Report Date
- September 2017
Achievements in Last Period
- Dev migration completed, tested and signed off.
- Preparation for the migration to TEST.
Issues
- Timeline has slipped a couple of weeks due to annual leave in September, however will not impact the closure date.
Next Steps
- Migrate to TEST
- Integration testing
- UAT
Milestones
13-Oct-2017 | Integration |
20-Oct-2017 | Acceptance |
31-Oct-2017 | DELIVERY |
30-Nov-2017 | CLOSURE |
- Approved budget
- 25.0 days
- Activity this month
- 20.0 days
- Activity this year
- 27.0 days
- Activity to date
- 49.0 days
- Estimate to complete current year
- 18.0 days
- Estimate to complete future years
- 0.0 days