Report for August 2017
- Report Date
- August 2017
Achievements in Last Period
- DEV and TEST data is now refreshed from LIVE
- Milestones replaned
- Risks reviewed and removed / added as necessary
- Patch update to PURE not required. There is a patch update required to Oracle 12, but is included in 12.2. As we are moving to 12.2, there is no need to patch Oracle either.
Issues
- Delay in starting the refresh of data as the annual rollover of Finance data had to be completed before backups could be taken from PURE LIVE.
- Cost has put the project into AMBER as 10 days were originally allocated to the project for 17/18, but due to delays in 16/17 in getting resource the anticipated work was not carried out and been moved into the 17/18 year. A further 16 days are required for this project.
Next Steps
- Review previous project activity, ie the TAD and the plan are up to date.
- begin the migration to DEV
- Integration testing
- Acceptance testing
Milestones
15-Sep-2017 | Build |
20-Sep-2017 | Integration |
27-Sep-2017 | Acceptance |
05-Oct-2017 | DELIVERY |
30-Nov-2017 | CLOSURE |
- Approved budget
- 10.0 days
- Activity this month
- 3.0 days
- Activity this year
- 2.0 days
- Activity to date
- 24.0 days
- Estimate to complete current year
- 26.0 days
- Estimate to complete future years
- 0.0 days