RES062: PURE Upgrade to Oracle 12c Status Report - DRAFT
- Report Date
- April 2016
Achievements this period
Initial meetings set up with Jill Nicoll, Mark Lang and James Toon to introduce myself and discuss initial RES062: PURE Upgrade to Oracle 12c expectations and dependencies between PURE upgrade and Oracle 11g-12c.
The previous PURE migration to Oracle 11g was approx 2 years ago. Whilst Oracle 12c tech is slightly different the process can potentially be cut and paste.
Similarly worst/likely/best time estimates will be similar, however, downtime has been reduced to approx 1hr.
Gillian Henderson has been identified as Dev Tech Lead
Issues
NONE
Next Steps
Complete Planning
Complete 3Point Estimate
Commence Business Analysis
Milestones
Target date | Previous Date | Title | Complete |
20/05/16 | 20/05/16 | Planning | NO |
17/10/16 | 17/10/16 | Delivery | NO |
16/12/16 | 16/12/16 | Closure | NO |
- Approved budget
- 45.0 days
- Activity this month
- 1.3 days
- Activity this year
- 1.4 days
- Activity to date
- 1.4 days
- Estimate to complete current year
- 36.4 days
- Estimate to complete future years
- 8.4 days