Project Brief Overview 07/04/16 Jill Nicoll

Attendees:

Nikki Hackett Reed

Jill Nicoll

Content

  • Discuss with Production Support/Apps Management re coordination of back log updates
  • Locate the last oracle upgrade project and/or PM’s
  • Guidelines for R&R/Comms Plan
  • Arrange a meeting with James Toon & Suran regarding any outstanding upgrades to PURE and when we draw the line on further upgrades during the delivery of the project
  • Organise a kick off meeting w/c 18/04

Project Info

Project
PURE Upgrade to Oracle 12c
Code
RES062
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Start Date
06-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Dec-2017
Programme Priority
2
Overall Priority
Normal
Category
Compliance