May Progress Report

Report Date
May 2013

Achievements in Last Period

  • Brief complete with the agreed result of the proof of concept results
  • Authentication password set up for 2 ids in user acceptance testing.
  • Acceptance complete
  • Delivery complete
  • Authentication password set up for 10 ids in LIVE
  • Deployment sign off review complete
  • Business sponsor has already found that requests are coming in for access, even before it has been advertisted.
  • Closure complete - Completion Report

Issues

  • None

Next Steps

  • None
Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
21.0 days
Activity this month
3.0 days
Activity this year
19.0 days
Activity to date
19.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
PURE Web Services Implementation
Code
RES041
Programme
Z. Research (RES) (closed August 2017)
Project Manager
Anne Mathison
Project Sponsor
Alexis Cornish
Current Stage
Close
Status
Closed
Start Date
25-Sep-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
30-May-2013