Monthly Progress Report
- Report Date
- June 2015
Achievements in last period:
- Oracle TYE Bug Fix Patch tested in DEV
- Oracle TYE Bug Fix Patch implemented to TEST
- Oracle TYE Bug Fix Patch tested in TEST
- HR Jar file work carried out in DEV
- Agreed plan and milestone dates for HR Jar file for Test and Live
- HR Jar file regression tested in DEV
- HR Jar file work carried out in TEST
- Oracle provided a work around for last TYE security patch
- Oracle TYE work around security patch investigated and proven in Dev
- Oracle TYE work around security patch now continuting via support under unidesk call I150624-0740 as Payroll did not want the current plan affected with Go Live on Jul-6
- HR Jar file regression tested in TEST, and signed off by HR and Payroll - 2-Jul
Issues:
- None
Next Steps:
- HR Jar File and Oracle TYE Bug fix to proceed to Live on 6-Jul
- Project Closure to be completed
- Project to be closed
Milestones:
17-Jul-2015 | HR Jar File Live |
31-Jul-2015 | Closure |
- Approved budget
- 110.0 days
- Activity this month
- 6.2 days
- Activity this year
- 95.6 days
- Activity to date
- 95.6 days
- Estimate to complete current year
- 5.7 days
- Estimate to complete future years
- 0.0 days