Monthly Progress Report
- Report Date
- May 2015
Achievements in last period:
- HR Jar file investigated and process agreed
- Oracle TYE Bug Fix Patch information received.
- TYE Bug Fix Patch completed in Dev
Issues:
- None
Next Steps:
- Oracle TYE Bug Fix Patch to test in DEV
- Oracle TYE Bug Fix Patch to implement to TEST
- Oracle TYE Bug Fix Patch to test in TEST
- HR Jar file work carried out in DEV
- Agree plan and milestone dates for HR Jar file for Test and Live
- HR Jar file regression tested in DEV
- HR Jar file work carried out in TEST
- HR Jar file regression tested in TEST
- Confirm if Oracle have replied on the last security patch and if it is required - if no response it will not delay this project
Milestones:
HR Jar file milestones dates to be agreed for Dev, Test and Live
15-Jul-2015 | Closure |
- Approved budget
- 110.0 days
- Activity this month
- 5.6 days
- Activity this year
- 89.3 days
- Activity to date
- 89.3 days
- Estimate to complete current year
- 16.1 days
- Estimate to complete future years
- 0.0 days