Monthly Progress Report

Report Date
April 2015

 For April the Shared Parental Leave, remaining 2 Security patches and the Oracle TYE bug fix (including HR Global) was completed in Live on 6-Apr-15 and signed off on 28-Apr-15.

Achievements in last period:

  • LIVE Shared Parental Leave patches + security patches + Oracle Bug fix (including HR Global) (deployed 6-Apr)
  • P2 Test P60 TESTED (completed 8-Apr)
  • P2 Live P60
  • P60 arrived at home addresses 1st May
  • Investigate HR Jar file and estimate
  • Phase 3 is not required this year and 20 days have been freed up to the programme

Issues:

  • None

Next Steps:

  • Confirm if Oracle have replied on the last security patch and if it is required - if no response it wil not delay this project
  • HR Jar file work carried out in Dev
  • Agree plan and milestone dates for HR Jar file for Test and Live 

Milestones: 

 HR Jar file milestones dates to be agreed for Dev, Test and Live

15-Jul-2015Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
110.0 days
Activity this month
8.0 days
Activity this year
84.0 days
Activity to date
84.0 days
Estimate to complete current year
18.0 days
Estimate to complete future years
0.0 days

Project Info

Project
HR and Payroll Annual Maintenance 14/15
Code
PPP003
Programme
Z. Payroll and Pensions (PPP) (closed)
Project Manager
Anne Mathison
Project Sponsor
Terry Fox
Current Stage
Close
Status
Closed
Start Date
29-Oct-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2015
Programme Priority
2
Overall Priority
Normal
Category
Compliance