Progress Report

Report Date
February 2015

February saw the implementation of the patches required for Tax Year End as well as the 75% of security patches.

Achievements in last period:

  • P1 RUP 7 LIVE - completed successfully
  • P2 TYE Planning patches - done 
  • P2 Planning Security patches -a significant number of patches
  • P2 TYE DEV patches + Security patches (6). Six of the 8 patches were progessed.
  • P2 TYE DEV + Security patches testing  as well as the oracle fix for TYE - completed
  • P2 TYE TEST patches + Security patches  + TYE Fix - completed
  • Oracle notice of patches for Shared Parental Leave for start of year 2014-15 needed before April Payroll. Oracle have confirmed the work and it has been planned

Issues:

  • None

Next Steps:

  • P2 TYE ASOR + Security patches testing + Oracle TYE fix (signed off 4-Mar)
  • P2 LIVE TYE Patching + security patches + Oracle TYE fix
  • P2 Dev P60
  • A security issue was raised with Oracle and we expect to be able to incorporate the remaining security patches with the Shared Parental Leave patch in April
  • DEV Shared Parental Leave patches + security patches to be implemented and tested
  • TEST Shared Parental Leave patches + security patches to be implemented and tested

Milestones: 

Live date for Shared Parental Leave to be confirmed

02-Mar-2015P2 TEST/ASOR TYE Patching + security patches
05-Mar-2015P2 LIVE TYE Patching + security patches
13-Mar-2015DEV Shared Parental Leave patches + security patches
16-Mar-2015P2 Dev P60
20-Mar-2015TEST Shared Parental Leave patches + security patches
DD-Apr-2015LIVE Shared Parental Leave patches + security patches
08-Apr-2015P2 TEST/ASOR P60
15-Apr-2015P2 LIVE P60
15-May-2015P3 Budget Design/Planinng (if req)
22-May-2015P3 Budget DEV Patching (if req)
05-Jun-2015P3 Budget TEST/ASOR Patching (if req)
12-Jun-2015P3 Budget LIVE Patching (if reg)
15-Jul-2015Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
130.0 days
Activity this month
23.0 days
Activity this year
56.0 days
Activity to date
56.0 days
Estimate to complete current year
68.0 days
Estimate to complete future years
0.0 days

Project Info

Project
HR and Payroll Annual Maintenance 14/15
Code
PPP003
Programme
Z. Payroll and Pensions (PPP) (closed)
Project Manager
Anne Mathison
Project Sponsor
Terry Fox
Current Stage
Close
Status
Closed
Start Date
29-Oct-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2015
Programme Priority
2
Overall Priority
Normal
Category
Compliance