Monthly Report
- Report Date
- December 2014
Clone LIVE to TEST had to replanned in December, due to resourcing and other work that required completed before end of December. The work was replanned in Janusary and the milestones reflect this information
Achievements in last period:
- Dev was cloned from LIVE by project HRS081
- P1 Design /Planning (Pre-requisite patches - RUP 7)
Issues:
- None
Next Steps:
- P1 RUP 7 DEV patching to complete
- P1 RUP 7 DEV Testing to complete
- Clone LIVE to TEST
- P1 RUP 7 TEST patching to complete
- P1 RUP 7 Acceptance complete
Milestones:
14-Jan-2015 | P1 DEV Pre-requisite Patching + DEV test |
19-Jan-2015 | P1 TEST Clone of LIVE |
30-Jan-2015 | P1 TEST/ ASOR Pre-requisite Patching |
04-Feb-2015 | P2 TYE Design/Planning Patching + Security |
05-Feb-2015 | P1 LIVE Pre-requisite patching |
17-Feb-2015 | P2 DEV TYE Patching + security patches |
02-Mar-2015 | P2 TEST/ASOR TYE Patching + security patches |
05-Mar-2015 | P2 LIVE TYE Patching + security patches |
16-Mar-2015 | P2 Dev P60 |
08-Apr-2015 | P2 TEST/ASOR P60 |
15-Apr-2015 | P2 LIVE P60 |
15-May-2015 | P3 Budget Design/Planinng (if req) |
22-May-2015 | P3 Budget DEV Patching (if req) |
05-Jun-2015 | P3 Budget TEST/ASOR Patching (if req) |
12-Jun-2015 | P3 Budget LIVE Patching (if req) |
15-Jul-2015 | Closure |
- Approved budget
- 130.0 days
- Activity this month
- 4.0 days
- Activity this year
- 14.0 days
- Activity to date
- 14.0 days
- Estimate to complete current year
- 116.0 days
- Estimate to complete future years
- 0.0 days