Monthly Progress Report

Report Date
November 2014

Achievements in last period:

  • Set up Project Website and ASTA
  • Project Brief drafted
  • Project Team meeting held to agree timelines and milestone project dates
  • Agreed at meeting to suspend PPP001 - Automation of Maternity, Paternity and Adoption Pay Calculations until July-15
  • Approval of Project Brief atv WIS.

Issues:

  • None

Next Steps for Dec-14 and Jan-15:

  • Confirm that DEV has been cloned from LIVE by project HRS081
  • Clone LIVE to TEST
  • P1 Review RUP 7 Patching  and complete task list
  • P1 Handover/Training to SASG Dev
  • P1 RUP 7 DEV complete
  • P1 RUP 7 TEST complete
  • P1 RUP 7 Acceptance complete

Milestones: 

12-Dec-2014P1 Design/Planning (Pre-Requisite Patches - RUP 7)
15-Dec-2014P1 DEV is copy of LIVE
18-Dec-2014P1 TEST Clone of LIVE
16-Jan-2015P1 DEV Pre-requisite Patching + DEV test
30-Jan-2015P1 TEST/ UAT Pre-requisite Patching
04-Feb-2015P2 TYE Design/Planning Patching + Security
05-Feb-2015P1 LIVE Pre-requisite patching
17-Feb-2015P2 DEV TYE Patching + security patches
02-Mar-2015P2 TEST TYE Patching + security patches
05-Mar-2015P2 LIVE TYE Patching + security patches
15-Apr-2015P2 P60
15-May-2015P3 Budget Design/Planinng (if req)
22-May-2015P3 Budget DEV Patching (if req)
05-Jun-2015P3 Budget TEST Patching (if req)
12-Jun-2015P3 Budget LIVE Patching (if req)
15-Jul-2015
Closure

 

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
100.0 days
Activity this month
7.5 days
Activity this year
8.3 days
Activity to date
8.3 days
Estimate to complete current year
121.4 days
Estimate to complete future years
0.0 days

Project Info

Project
HR and Payroll Annual Maintenance 14/15
Code
PPP003
Programme
Z. Payroll and Pensions (PPP) (closed)
Project Manager
Anne Mathison
Project Sponsor
Terry Fox
Current Stage
Close
Status
Closed
Start Date
29-Oct-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2015
Programme Priority
2
Overall Priority
Normal
Category
Compliance