Monthly Progress Report
- Report Date
- November 2014
Achievements in last period:
- Set up Project Website and ASTA
- Project Brief drafted
- Project Team meeting held to agree timelines and milestone project dates
- Agreed at meeting to suspend PPP001 - Automation of Maternity, Paternity and Adoption Pay Calculations until July-15
- Approval of Project Brief atv WIS.
Issues:
- None
Next Steps for Dec-14 and Jan-15:
- Confirm that DEV has been cloned from LIVE by project HRS081
- Clone LIVE to TEST
- P1 Review RUP 7 Patching and complete task list
- P1 Handover/Training to SASG Dev
- P1 RUP 7 DEV complete
- P1 RUP 7 TEST complete
- P1 RUP 7 Acceptance complete
Milestones:
12-Dec-2014 | P1 Design/Planning (Pre-Requisite Patches - RUP 7) | |
15-Dec-2014 | P1 DEV is copy of LIVE | |
18-Dec-2014 | P1 TEST Clone of LIVE | |
16-Jan-2015 | P1 DEV Pre-requisite Patching + DEV test | |
30-Jan-2015 | P1 TEST/ UAT Pre-requisite Patching | |
04-Feb-2015 | P2 TYE Design/Planning Patching + Security | |
05-Feb-2015 | P1 LIVE Pre-requisite patching | |
17-Feb-2015 | P2 DEV TYE Patching + security patches | |
02-Mar-2015 | P2 TEST TYE Patching + security patches | |
05-Mar-2015 | P2 LIVE TYE Patching + security patches | |
15-Apr-2015 | P2 P60 | |
15-May-2015 | P3 Budget Design/Planinng (if req) | |
22-May-2015 | P3 Budget DEV Patching (if req) | |
05-Jun-2015 | P3 Budget TEST Patching (if req) | |
12-Jun-2015 | P3 Budget LIVE Patching (if req) | |
15-Jul-2015 |
|
- Approved budget
- 100.0 days
- Activity this month
- 7.5 days
- Activity this year
- 8.3 days
- Activity to date
- 8.3 days
- Estimate to complete current year
- 121.4 days
- Estimate to complete future years
- 0.0 days