Draft Status Report for period ending 1 November 2019

Report Date
November 2019

Key Activities/Milestones since last report

Key Activities since last report

TOM has now been completed based on the workshops and the content has been reviewed by the project sponsor.  The principles will be discussed at SEP Board on 31 October 

Internal Audit confirmed that they would like to see some minor additions to the TOM to confirm how policies will be reported to University Committees and what escalation there will be if policies become overdue.  The requested additions have been made and a new version of the TOM sent to internal audit 

 

The business case document is 80% complete and will be finalised based on the comments from 31 October SEP Board 

Upcoming Activities/Milestones

Upcoming Activities

Finalise Business case document and take through review processes 

Draft and circulate slides/papers for SEP Board on 9 December 

 

 

 

Upcoming Milestones

None this period 

 

 

Key Risks and Issues

 
New/Changed Risks

Nothing to report this period 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
On track
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
University Policy Framework
Code
P0326
Management Office
Service Excellence PMO
Project Manager
Ruth Wilson
Project Sponsor
Tracey Slaven
Current Stage
Plan
Status
In Progress
Project Classification
Transform
Start Date
31-Oct-2018
Planning Date
11-Feb-2019
Delivery Date
08-Dec-2019
Close Date
20-Dec-2019