Project journal
| Title | Description | Author | Post date |
|---|---|---|---|
| IS Applications Projects Update 26 April 2019 |
Projects to be Started Protecting Student Data in the EDW INF145 CMVM Curriculum Mapping Tool – Requirements MVM133 Unidesk Procurement SMI024 SITS RedHat Operating System Automated Deployment & Upgrade SAC080
Projects at the End of Planning |
Glenda Growdon | 30-Apr-2019 |
| IS Applicsations Projects Update 19 April 2019 |
Projects to be Started Development and Alumni CRM Procurement USG014 PCI DSS FIN129
Projects at the End of Planning None this week
Projects Delivered |
Glenda Growdon | 22-Apr-2019 |
| IS Applications Projects Update - 12 April 2019 |
Projects to be Started COSHH Updates HAS006
Projects at the End of Planning Annual Wiki Upgrade COM046 – home page – project brief |
Glenda Growdon | 15-Apr-2019 |
| IS Applications Projects Update 5 April 2019 |
Projects to be Started IT and Library Business Service Readiness for Start of Term 2019/20 ISG017 UniDesk for Malta SMI023 Create MBChB ranking Reports in Bi-Suite MVM132
Projects at the End of Planning |
Glenda Growdon | 08-Apr-2019 |
| IS Applications Projects Update |
Projects to be Started Geosciences Database Migration SCE015
Projects at the End of Planning Lecture Recording Transition Phase MLE005 –home page – project brief
Projects Delivered |
Glenda Growdon | 02-Apr-2019 |
| IS Applications Projects Update - 22 March 2019 |
Projects to be Started G-Cloud replacement of FOI Request Planning Tool STU265
Projects at the End of Planning Embed and Optimise UX Services DTI045 – home page – project brief
|
Glenda Growdon | 26-Mar-2019 |
| IS Applications Projects Update 15 March 2019 |
Projects to be Started Essential Finance System Compliance Updates and Document Revitalisation FIN126 ECA Induction Content Structure Design HSS026 PG Admissions Improvements SAC079
Projects at the End of Planning |
Glenda Growdon | 19-Mar-2019 |
| IS Applications Projects Update 8 March 2019 |
Projects to be Started Move IS based Oracle Databases to VMs INF142 Risk Management System Procurement CSG015 HR HESA Staff Return 18/19 HRS097 Clearing 2019 USG013
Projects at the End of Planning |
Glenda Growdon | 12-Mar-2019 |
| IS Applications Projects Update 1 March 2019 |
Projects to be Started DLAS Learning Analytics DLAS010 Learn Upgrade TEL060 Estates CAFM System Future Direction EST121
Projects at the End of Planning |
Glenda Growdon | 05-Mar-2019 |
| IS Applications Projects Update 22 February 2019 |
Projects to be Started None this week
Projects at the End of Planning IS Student Recruitment Solution ISG015 – home page – project brief |
Glenda Growdon | 26-Feb-2019 |
| IS Applications Projects Update 8 February 2019 |
Projects to be Started None this week
Projects at the End of Planning Pure Upgrade v5.13 to v5.15 RIS007 – home page – project brief |
Glenda Growdon | 12-Feb-2019 |
| IS Applications Projects Update 1 February 2019 |
Projects to be Started Logging Data Retention INF134 Annual DR Review and Tests INF138 SPQS Improvements HSS029 Returning Students Online Matriculation: Key Data Collection & Configuration SAC078
Projects at the End of Planning |
Glenda Growdon | 05-Feb-2019 |
| IS Applications Projects Update 25 January 2019 |
Projects to be Started Identity and Access Management (IDAM) Roadmap ISG016 FPM Upgrade FIN128 Clasync Bi-Annual Upgrade COM048
Projects at the End of Planning |
Glenda Growdon | 29-Jan-2019 |
| IS Applications Projects Update 18 January 2019 |
Projects to be Started None this week
Projects at the End of Planning Data Futures Requirements SAC077 – home page – project brief |
Glenda Growdon | 21-Jan-2019 |
| IS Applications Projects Update 11January 2019 |
Projects to be Started Annual Wiki Upgrade COM046 Moodle Upgrade TEL059
Projects at the End of Planning Establishing Platform data store for DLAS DLAS012 – home page – project brief
|
Glenda Growdon | 14-Jan-2019 |
| IS Applications Projects Update 21 December 2018 |
Projects to be Started IS Student Recruitment Solution ISG015 Subtitling for Media MLE007
Projects at the End of Planning Encryption at Rest INF144 – home page – project brief |
Glenda Growdon | 07-Jan-2019 |
| IS Applications Projects Update 14 December 2018 |
Projects to be Started None this week
Projects at the End of Planning EdWeb Development UWP023 – home page – project brief
Projects Delivered |
Glenda Growdon | 18-Dec-2018 |
| IS Applications Projects Update 7 December 2018 |
Projects to be Started Migration of 12 Applications Developed in Biomedical Sciences to Central Support – Analysis and Strategy MVM131 Digitised Library Workflows Options Appraisal DLIB001 Dgital Datasets DLIB002 IDM Database Upgrade COM045
Projects at the End of Planning |
Glenda Growdon | 11-Dec-2018 |
| IS Applications Projects Update 30 November 2018 |
Projects to be Started Fire Management System Implementation HAS005 Estates Document Management System EST100
Projects at the End of Planning None this week
Projects Delivered |
Glenda Growdon | 04-Dec-2018 |
| IS Applications Projects Update - 23 November 2018 |
Projects to be Started REF2021 Data Requirements Analysis RIS008 A Digital Archive for Scottish Studies – Appraisals and Strategy HSS028 Lecture Recording Transition Phase MLE005 Data Futures Requirements Analysis and Implementation SAC077
Projects at the End of Planning |
Glenda Growdon | 27-Nov-2018 |