IS Applications Project Update – 25 November 2016

New Projects

None this week

 

Projects at the End of Planning

SITS Software Upgrade to 9.3.0 - SAC058 – Homepage / Project Brief

Enterprise Data Warehouse (EDW) Delivery (Proof of Concept) – COM029 – Homepage / Project Brief

 

Projects Delivered

Working Time Capture and Reporting (APEX report deployment) – HRS091 – Homepage / Delivery Milestone

 

Project Closures and Withdrawals

None this week

Project Info

Project
Project Management Office (PMO)
Code
P0123
Programme
PMO Test Programme
Project Manager
Rhian Davies
Project Sponsor
Mark Ritchie
Current Stage
Execute
Status
Not Started
Start Date
09-Sep-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a