July Report

Report Date
July 2019

April report - no progress.

Project Status
RAG Status
Time
AMBER
Cost
RED
Scope
RED
Overall
RED
Change Status
Time
Moderate
Cost
Significant
Scope
Significant
Overall
Significant
Has formal escalation taken place?
Yes
Escalated to
Project Sponsor
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
EXAMPLE - Putting a man on the moon
Code
P0093
Programme
EXAMPLE - example programme for demonstration purposes (EXAMPLE)
Project Manager
Dawn Holmes
Project Sponsor
Rhian Davies
Current Stage
Execute
Status
In Progress
Start Date
04-Jan-2016
Planning Date
29-Apr-2016
Delivery Date
31-Jul-2020
Close Date
30-Oct-2020
Overall Priority
Highest