Report for January 2017

Report Date
January 2017

Achievements

  • achievement
  • achievement

 

Issues

  • issue

 

Next Steps

  • next step
  • next step
Project Status
RAG Status
Overall
RED
RAG Commentary
Issue - project sponsor does not have time to engage with the project, deadline for planning missed, issue escalated with the programme owner, meeting next week to discuss options, including suspension of project.
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
EXAMPLE - Putting a man on the moon
Code
P0093
Programme
EXAMPLE - example programme for demonstration purposes (EXAMPLE)
Project Manager
Dawn Holmes
Project Sponsor
Rhian Davies
Current Stage
Execute
Status
In Progress
Start Date
04-Jan-2016
Planning Date
29-Apr-2016
Delivery Date
31-Jul-2020
Close Date
30-Oct-2020
Overall Priority
Highest