- Report Date
- January 2016
Achievement this period
- Astronauts have all been recruited and training has started on schedule
- Spacecraft design has been signed off by NASA and the engineers are on site to commence the build
- The foundations for the command centre have been laid
Issues
- The bad weather has meant that the concrete in the command centre foundations is taking longer to set than anticipated
Next steps
- Construct the walls, floors and ceiling of the command centre
- Comment the build of the spacecraft
- Complete astronaut training
- Approved budget
- 2920.0 days
- Activity this month
- 30.0 days
- Activity this year
- 90.0 days
- Activity to date
- 370.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days
This article was published on