Status report for Jan 2016

Report Date
January 2016

Achievement this period

  • Astronauts have all been recruited and training has started on schedule
  • Spacecraft design has been signed off by NASA and the engineers are on site to commence the build
  • The foundations for the command centre have been laid

Issues

  • The bad weather has meant that the concrete in the command centre foundations is taking longer to set than anticipated

Next steps

  • Construct the walls, floors and ceiling of the command centre
  • Comment the build of the spacecraft
  • Complete astronaut training

 

Target date Title
01-Feb-2016 Astronauts ready
01-Feb-2016 Command Centre ready
15-Feb-2016 Spacecraft ready
18-Feb-2016 Ready for launch
22-Mar-2016 Mission completed
31-Mar-2016 Project closes

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
2920.0 days
Activity this month
30.0 days
Activity this year
90.0 days
Activity to date
370.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
EXAMPLE - Putting a man on the moon
Code
P0093
Programme
EXAMPLE - example programme for demonstration purposes (EXAMPLE)
Project Manager
Dawn Holmes
Project Sponsor
Rhian Davies
Current Stage
Execute
Status
In Progress
Start Date
04-Jan-2016
Planning Date
29-Apr-2016
Delivery Date
31-Jul-2020
Close Date
30-Oct-2020
Overall Priority
Highest