Report for December 2019
- Report Date
- December 2019
Achievements this Period
- Development is now deemed complete.
- A change record was approved to move milestone dates from the end of December to the end of January, 2020.
Issues
- Non-availability of resource to undertake Equity Impact Assessment testing this side of Christmas.
Next Steps
- Penetration testing to be undertaken.
- Oversee project preparations for implementation and actual deployment.
Milestones
| Deliver | Deployment | 30-Jan-2020 |
| Deliver | Deployment Sign-off Review (DSOR) | 31-Jan-2020 |
| Close | Closure Report Sign-off | 31-Jan-2020 |
- Approved budget
- 120.0 days
- Activity this month
- 9.5 days
- Activity this year
- 96.5 days
- Activity to date
- 96.5 days
- Estimate to complete current year
- 23.5 days
- Estimate to complete future years
- 0.0 days