Report for November 2019
- Report Date
- November 2019
Achievements this Period
- Design and development effort is progressing close to plan. Focus is mainly on allowing for creation of multiple surveys and clearing the backlog of Jira issues.
- Regular review meetings have been held with good continued attendance.
- An Equality Impact Assessment form has been populated.
Issues
- The 3rd party undertaking of penetration testing could not be organised this side of Christmas to align with expected build complete.
Next Steps
- Conclude user interface design and software development.
- Arrange for independent Equality Impact Assessment testing.
- Arrange for independent penetration testing.
- Raise change record to move milestone dates from the end of December to the end of January, 2020.
- Oversee project preparations for implementation and actual deployment.
Milestones
| Deliver | Deployment | 30-Jan-2020 |
| Deliver | Deployment Sign-off Review (DSOR) | 31-Jan-2020 |
| Close | Closure Report Sign-off | 31-Jan-2020 |
- Approved budget
- 120.0 days
- Activity this month
- 13.8 days
- Activity this year
- 87.3 days
- Activity to date
- 87.3 days
- Estimate to complete current year
- 23.5 days
- Estimate to complete future years
- 0.0 days