Report for October 2019
- Report Date
- October 2019
Achievements this Period
- The Data Privacy Impact Assessment (DPIA) has been concluded and signed-off.
- Work has been re-prioritised with an extension to time to enable a more complete final product.
- Additional funding has been agreed to accommodate extra work, particularly that of a solution to gather survey data.
Issues
- None.
Next Steps
- Conclude user interface design and software development.
- Population of Equality Impact Assessment Form.
- Schedule a penetration test.
- Continue with weekly business and technical team reviews with a focus on the presentation layer of the web-site build.
Milestones
| Deliver | Deployment | 20-Dec-2019 |
| Deliver | Deployment Sign-off Review (DSOR) | 31-Dec-2019 |
| Close | Closure Report Sign-off | 31-Dec-2019 |
- Approved budget
- 120.0 days
- Activity this month
- 15.0 days
- Activity this year
- 73.5 days
- Activity to date
- 73.5 days
- Estimate to complete current year
- 31.5 days
- Estimate to complete future years
- 0.0 days