Report for September 2019
- Report Date
- September 2019
Achievements this Period
- The Project Brief was signed-off.
- Two iterations of work (managed as Jira issues) have been undertaken.
- A re-focus on project governance is underway with the assignment of a replacement manager to the project.
Issues
- Additional Jira issues have been raised as requirements.
- Project budget overspend and planned delivery dates are at risk.
Next Steps
- All open Jira issues in the product backlog need to be estimated for remaining work effort.
- A meeting is to be arranged to prioritise open issues as a third iteration of a work package.
- A review is to be scheduled with the business to agree what makes up the offering of Minimum Viable Product.
Milestones
| Plan | End of plan | 16-Aug-2019 |
| Execute | End of foundations | 29-Aug-2019 |
| Execute | End of development iteration 1 | 12-Sep-2019 |
| Execute | End of development iteration 2 | 26-Sep-2019 |
| Execute | End of development iteration 3 | 10-Oct-2019 |
| Deliver | Iteration release - go live | 11-Oct-2019 |
| Deliver | End of maintenance iteration | 14-Oct-2019 |
| Close | Lessons learned | 15-Oct-2019 |
| Close | Closure report | 18-Oct-2019 |
- Approved budget
- 80.0 days
- Activity this month
- 32.0 days
- Activity this year
- 58.5 days
- Activity to date
- 58.5 days
- Estimate to complete current year
- 21.5 days
- Estimate to complete future years
- 0.0 days