Report for October 2019

Report Date
October 2019

Achievements this period

  • None

Issues

  • Programme Manager and Sponsor lack availability to complete closure

Next Steps

  • Write closure report
  • Close Project
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
20.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.8 days
Estimate to complete future years
0.0 days

Project Info

Project
CMVM Data Storage Strategy
Code
MVM311
Programme
MVM Research (MVMRES)
Management Office
ISG PMO
Project Manager
Muriel Mewissen
Project Sponsor
Sheila Fraser
Current Stage
Close
Status
In Progress
Project Classification
Run
Start Date
02-Nov-2018
Planning Date
13-Nov-2018
Delivery Date
30-Apr-2019
Close Date
01-Nov-2019
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation