Report for December 2019
- Report Date
- December 2019
Achievements this Period
- Successful Admissions Assessment days took place for the first time with no issues during the days and with great feedback from the assessors on how straightforward the process and software was.
- Admissions lead has begun to use the data and is delighted with the information - the desired outcome has been achieved.
- Lessons learned completed for Admissions - key success factor was how thoroughly prepared the Admissions team were for the Exam Fit days in September, which meant their requirements were very clearly understood.
Issues
- College is working with supplier on option to have a separate TEST instance for the Vets/BMTO.
Next Steps
- Business completing agreed steps to ensure the MBChB HCP Admission Assessment days take place smoothly
- Detailed planning for the Vets and BMTO work
Milestones
Stage | Milestone | Due Date | Previous Date | Complete |
---|---|---|---|---|
Execute | BMTO Training Day | 24-Feb-2020 | No date available | No |
Execute | Vets Training Day | 25-Feb-2020 | No date available | No |
Execute | Vets Pilot | 17-Mar-2020 | No date available | No |
Deliver | Vets LIVE | 29-May-2020 | No date available | No |
Deliver | Delivery of all Practique elements | 17-Jul-2020 | 31-May-2020 | No |
Deliver | BMTO LIVE | 17-Jul-2020 | No date available | No |
Close | Project Closure approved | 31-Jul-2020 | 20-Jun-2020 | No |
- Approved budget
- 35.0 days
- Activity this month
- 1.0 day
- Activity this year
- 14.0 days
- Activity to date
- 14.0 days
- Estimate to complete current year
- 20.0 days
- Estimate to complete future years
- 0.0 days