Report for November 2019

Report Date
November 2019

Achievements this Period

Issues

  • None

Next Steps

  • Confirmation of Business Readiness for Admissions Assessments w/c 9th
  • Conclusion of ipads build
  • Admissions Assessment days w/c 9th December
  • Review/Lessons Learned for Assessment days

Milestones

Stage Milestone Due Date Previous Date Complete
Execute Admissions Business Ready checkpoint 02-Dec-2019 No date available No
Execute Admissions LIVE 09-Dec-2019 No date available No
Execute BMTO Training Day 24-Feb-2020 No date available No
Execute Vets Training Day 25-Feb-2020 No date available No
Execute Vets Pilot 17-Mar-2020 No date available No
Deliver Vets LIVE 29-May-2020 No date available No
Deliver Delivery of all Practique elements 17-Jul-2020 31-May-2020 No
Deliver BMTO LIVE 17-Jul-2020 No date available No
Close Project Closure approved 31-Jul-2020 20-Jun-2020 No

 

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Project progressing to plan
Change Status
Time
Moderate
Cost
Moderate
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
No
Change Commentary
As part of the brief approval, changes in major milestones and budget were approved. The Delivery and Closure milestones were revised to later dates to cover the BMTO exam work in July. The budget for this project decreased from 50 days to 35 days.
Activity
Approved budget
35.0 days
Activity this month
2.6 days
Activity this year
13.1 days
Activity to date
13.1 days
Estimate to complete current year
21.9 days
Estimate to complete future years
0.0 days

Project Info

Project
Practique Roll-Out
Code
MVM136
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Susan Ridder-Patrick
Project Sponsor
Susan Rhind
Current Stage
Plan
Status
In Progress
Project Classification
Grow
Start Date
20-Sep-2019
Planning Date
10-Oct-2019
Delivery Date
17-Jul-2020
Close Date
31-Jul-2020
Overall Priority
Normal
Category
Discretionary