Report for September 2019

Report Date
September 2019

Achievements in this period

  • Project Started this month
  • Contractual arrangements formally concluded with Procurement and the Supplier
  • Exam Fit on-site days scheduled with Supplier, Vets, Admissions and BMTO

Issues

  • None

Next Steps

  • Complete Brief
  • Arrange on-site days for training for Admissions, Vets and BMTO

Milestones

Stage Milestone Due Date Complete
Plan Project brief approval 10-Oct-2019 No
Deliver Delivery of all Practique elements 31-May-2020 No
Close Project Closure approved 20-Jun-2020 No
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
50.0 days
Activity this month
2.9 days
Activity this year
2.9 days
Activity to date
2.9 days
Estimate to complete current year
42.7 days
Estimate to complete future years
0.0 days

Project Info

Project
Practique Roll-Out
Code
MVM136
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Susan Ridder-Patrick
Project Sponsor
Susan Rhind
Current Stage
Plan
Status
In Progress
Project Classification
Grow
Start Date
20-Sep-2019
Planning Date
10-Oct-2019
Delivery Date
17-Jul-2020
Close Date
31-Jul-2020
Overall Priority
Normal
Category
Discretionary

Documentation