Practique Roll-Out - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
December 2019 GREEN 35.0 days 14.0 days 20.0
Content
Status
In Progress
Current Stage
Plan
Start Date
Friday, 20 September 2019
Planning Date
Thursday, 10 October 2019
Delivery Date
Friday, 17 July 2020
Close Date
Friday, 31 July 2020
Project information
Project Code
MVM136
Programme
MVM Learning and Teaching (MVMLAT)
Session
19/20
Organisational Unit
College of Medicine & Veterinary Medicine
Project Management Office (if relevant)
ISG PMO
Responsibility
User Services Directorate
Project Category
Discretionary
Project Classification
Grow
Funding Source
College Ring-Fenced
Overall Priority
Normal
Student Impact
Project deliverables will be used by students