Report for October 2019

Report Date
October 2019

Achievements

  • Tutor set functionality added to the system
  • Backlog of tickets requiring review now cleared
  • Majority of evaluation creation and response functionality now implemented

Issues

  • One team member has required further emergency leave this month, impacting on the amount of developers available to work on this project

Next Steps

  • Complete remaining evaluation creation and response functionality
  • Begin work on reports available in the system
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
The team has been affected by some periods of unexpected emergency leave this month. We expect completion of this project to be delayed by two to three weeks.
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Change Commentary
The team has been affected by some periods of unexpected emergency leave this month. We now expect the project to complete two to three weeks after our initial estimates. Developers will continue to be fully assigned to complete in December.
Activity
Approved budget
183.0 days
Activity this month
24.0 days
Activity this year
40.0 days
Activity to date
40.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
MBChB Evaluation System
Code
MVM134
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Andrew Millington
Project Sponsor
Sheila Fraser
Current Stage
Execute
Status
In Progress
Project Classification
Run
Start Date
09-Sep-2019
Planning Date
09-Sep-2019
Delivery Date
06-Dec-2019
Close Date
n/a
Overall Priority
Normal
Category
Discretionary

Documentation

Not available.