CMVM Curriculum Mapping Tool - Requirements - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2019 BLUE 42.0 days 35.0 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Wednesday, 17 April 2019
Planning Date
Friday, 10 May 2019
Delivery Date
Monday, 5 August 2019
Close Date
Friday, 9 August 2019
Project information
Project Code
MVM133
Programme
MVM Learning and Teaching (MVMLAT)
Session
19/20
18/19
Organisational Unit
College of Medicine & Veterinary Medicine
Project Management Office (if relevant)
ISG PMO
Responsibility
User Services Directorate
Project Category
Discretionary
Project Classification
Run
Funding Source
College Ring Fence
Overall Priority
Normal