Report for October 2019

Report Date
October 2019

Achievements in this Period

  • SSP, Student Data and Surveys and Development Services  resources secured for re-work
  • Demo session for Vets and BMS took place

Issues

  • Project milestones will need revised on confirmation of when business can complete testing

Next Steps

  • Student Data and Surveys team resource to complete updates to reports and provide initial check
  • MVM to check behaviour in LIVE is as expected
  • Close project

Milestones

These milestone are to be reviewed as noted in Issues above:

Stage Milestone Due Date Previous Date Complete
Deliver Delivery of reports complete 14-Oct-2019 16-Aug-2019 No
Close Close report complete and approved 15-Nov-2019 13-Sep-2019 No
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
This project has been delayed due to SSP resources being unavailable to complete work to planned dates. This means delivery to the Business in LIVE has been delayed The Project manager has all required resources assigned to new dates to complete the work between 15th and 27th November.
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
42.0 days
Activity this month
2.6 days
Activity this year
6.0 days
Activity to date
17.6 days
Estimate to complete current year
23.3 days
Estimate to complete future years
0.0 days

Project Info

Project
MBChB ranking reports in BI Suite
Code
mvm132
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Susan Ridder-Patrick
Project Sponsor
Nicola Crowley
Current Stage
Deliver
Status
In Progress
Project Classification
Run
Start Date
01-Apr-2019
Planning Date
26-Apr-2019
Delivery Date
31-Jan-2020
Close Date
28-Feb-2020
Overall Priority
Normal
Category
Discretionary

Documentation