Report for October 2019
- Report Date
- October 2019
Achievements in this Period
- SSP, Student Data and Surveys and Development Services resources secured for re-work
- Demo session for Vets and BMS took place
Issues
- Project milestones will need revised on confirmation of when business can complete testing
Next Steps
- Student Data and Surveys team resource to complete updates to reports and provide initial check
- MVM to check behaviour in LIVE is as expected
- Close project
Milestones
These milestone are to be reviewed as noted in Issues above:
| Stage | Milestone | Due Date | Previous Date | Complete |
|---|---|---|---|---|
| Deliver | Delivery of reports complete | 14-Oct-2019 | 16-Aug-2019 | No |
| Close | Close report complete and approved | 15-Nov-2019 | 13-Sep-2019 | No |
- Approved budget
- 42.0 days
- Activity this month
- 2.6 days
- Activity this year
- 6.0 days
- Activity to date
- 17.6 days
- Estimate to complete current year
- 23.3 days
- Estimate to complete future years
- 0.0 days