Report for September 2019

Report Date
September 2019

Achievements in this period

  • Resources for remaining work assigned
  • Support arrangements agreed with Student Data and reporting team
  • Promotion to LIVE completed (JIRA MVM132-2)
  • Demo session arranged for Vets and BMS
  • Project rescheduled to closure

Issues

  • The project completed a change control for milestones, withdrawing those not required and agreeing revised milestones to the remainder of the project.

Next Steps

  • Student Data and Surveys team resource to complete updates to reports and provide initial check
  • MVM to check behaviour in LIVE is as expected
  • Close project

Milestones

Stage Milestone Due Date Previous Date Complete  
Deliver Delivery of reports complete 14-Oct-2019 16-Aug-2019 No

view

Close Close report complete and approved 15-Nov-2019 13-Sep-2019 No

view

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Change Commentary
The project's delivery has been rescheduled and is just under the tolerance threshold of 2 months, therefore the RAG of within tolerance has been chosen.
Activity
Approved budget
42.0 days
Activity this month
0.8 days
Activity this year
3.3 days
Activity to date
14.9 days
Estimate to complete current year
26.9 days
Estimate to complete future years
0.0 days

Project Info

Project
MBChB ranking reports in BI Suite
Code
mvm132
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Susan Ridder-Patrick
Project Sponsor
Nicola Crowley
Current Stage
Deliver
Status
In Progress
Project Classification
Run
Start Date
01-Apr-2019
Planning Date
26-Apr-2019
Delivery Date
31-Jan-2020
Close Date
28-Feb-2020
Overall Priority
Normal
Category
Discretionary

Documentation