Report for June 2019

Report Date
June 2019
Achievements
  • New object promoted into Live
  • Progress team meeting held

Issues

  • SSP BA resource although scheduled was not able to support the project in early June - now scheduled for late June
  • MBChB were unable to complete manual ranking this month (due to assessment issues elsewhere) - no impact to project, will roll forward into uly

Next Steps

  • Schedule a further project team meeting  - targeting mid July
  • MBChB will be testing and SSP BA also due to deliver test content

 

Milestones

  • Milestones as of June 25
Stage Milestone Due Date Previous Date Complete
Deliver MBChB complete 2018-19 manual ranking 31-May-2019 No date available Started
Deliver Create new object(s) in universe 07-Jun-2019 No date available Yes
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
42.0 days
Activity this month
2.9 days
Activity this year
9.1 days
Activity to date
9.1 days
Estimate to complete current year
18.0 days
Estimate to complete future years
17.0 days

Project Info

Project
MBChB ranking reports in BI Suite
Code
mvm132
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Susan Ridder-Patrick
Project Sponsor
Nicola Crowley
Current Stage
Deliver
Status
In Progress
Project Classification
Run
Start Date
01-Apr-2019
Planning Date
26-Apr-2019
Delivery Date
31-Jan-2020
Close Date
28-Feb-2020
Overall Priority
Normal
Category
Discretionary

Documentation