Report for December 2019
- Report Date
- December 2019
Achievements in this Period
- Delivery and Closure milestones revised as Business Lead was unable to complete review of reports in LIVE due to unexpected leave and the need to priories Exams.
Issues
- None
Next Steps
- Completion of user checks on LIVE report
- Closure
Milestones
| Stage | Milestone | Due Date | Previous Date | Complete |
|---|---|---|---|---|
| Deliver | Delivery of reports complete | 31-Jan-2020 | 29-Nov-2019 | No |
| Close | Closure report complete and approved | 28-Feb-2020 | 20-Dec-2019 | No |
- Approved budget
- 42.0 days
- Activity this month
- 0.6 days
- Activity this year
- 8.3 days
- Activity to date
- 19.9 days
- Estimate to complete current year
- 20.4 days
- Estimate to complete future years
- 0.0 days