Report for April 2019
- Report Date
- April 2019
- Achievements
- Started the new project, Initiate and Planning - brief approved by project team and ISG WIS
Issues
- N/A, all new risks raised at project commencement
Next Steps
- Schedule a project team meeting in late May to assess progress
-
-
Milestones
- All new milestones created as project commencement - as of May 06
Stage Milestone Due Date Previous Date Complete Initiate complete initiation 05-Apr-2019 No date available Yes Plan Completion of project brief 03-May-2019 26-Apr-2019 Yes Deliver MBChB complete 2018-19 manual ranking 31-May-2019 No date available No Deliver Create new object(s) in universe 07-Jun-2019 No date available No
- Approved budget
- 42.0 days
- Activity this month
- 2.6 days
- Activity this year
- 2.6 days
- Activity to date
- 2.6 days
- Estimate to complete current year
- 39.4 days
- Estimate to complete future years
- 0.0 days