April 2016
- Report Date
- April 2016
Achievements in Last Period
- ITT approved by Project Board and published 05/04/16.
- Revised milestone dates agreed with Project Sponsor.
- Next three Project Board meetings aligned with key decision points on the timeline.
- Bidders conference held 21/04/16.
- Responses to supplier clarifications agreed and published by 28/04/16 deadline.
- Handover session (Project Sponsor, PM, Procurement Manager) ahead of Project Sponsor annual leave.
- Evaluators agreed for business sections of ITT.
- Most evaluators agreed for standard sections of ITT (awaiting some confirmations on staff availability).
- Briefing sessions arranged for staff scoring ITT (at Easter Bush and Dalhousie).
- Staff requested to complete Code of Conduct and Conflict of Interest Declarations.
Issues
- No major issues at present.
Next Steps
- ITT Mandatories to be scored 11/05/16 (to be agreed with IF/MF/TK in absence of Project Sponsor)
- ITT responses to be made available to scorers via procurement system from 12/05/16.
- Prepare update on evaluation process for Project Board.
- Review risks with Project Board.
- Review budget and resourcing.
The project current status is GREEN (ITT published, milestones revised but delivery date remains unchanged).
Milestones
| 11-May-2016 | Return of ITT |
| 12-May-2016 | ITT Evaluation Starts |
| 17-Jun-2016 | ITT Evaluation Phase Ends |
| 20-Jun-2016 | Award Recommendation |
| 21-Jun-2016 | Award Letter |
| 15-Aug-2016 | Contract Signed |
| 02-Sep-2016 | Closure |
- Approved budget
- 147.0 days
- Activity this month
- 9.0 days
- Activity this year
- 86.0 days
- Activity to date
- 86.0 days
- Estimate to complete current year
- 56.0 days
- Estimate to complete future years
- 7.0 days