April 2016

Report Date
April 2016

Achievements in Last Period

  • ITT approved by Project Board and published 05/04/16.
  • Revised milestone dates agreed with Project Sponsor.
  • Next three Project Board meetings aligned with key decision points on the timeline.
  • Bidders conference held 21/04/16.
  • Responses to supplier clarifications agreed and published by 28/04/16 deadline.
  • Handover session (Project Sponsor, PM, Procurement Manager) ahead of Project Sponsor annual leave.
  • Evaluators agreed for business sections of ITT.
  • Most evaluators agreed for standard sections of ITT (awaiting some confirmations on staff availability).
  • Briefing sessions arranged for staff scoring ITT (at Easter Bush and Dalhousie).
  • Staff requested to complete Code of Conduct and Conflict of Interest Declarations.

 

Issues

  • No major issues at present.

 

Next Steps

  • ITT Mandatories to be scored 11/05/16 (to be agreed with IF/MF/TK in absence of Project Sponsor)
  • ITT responses to be made available to scorers via procurement system from 12/05/16.
  • Prepare update on evaluation process for Project Board.
  • Review risks with Project Board.
  • Review budget and resourcing.

The project current status is GREEN (ITT published, milestones revised but delivery date remains unchanged).

Milestones

11-May-2016Return of ITT
12-May-2016ITT Evaluation Starts
17-Jun-2016ITT Evaluation Phase Ends
20-Jun-2016Award Recommendation
21-Jun-2016Award Letter
15-Aug-2016Contract Signed
02-Sep-2016Closure
Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
147.0 days
Activity this month
9.0 days
Activity this year
86.0 days
Activity to date
86.0 days
Estimate to complete current year
56.0 days
Estimate to complete future years
7.0 days

Project Info

Project
Tristan Replacement - Procurement
Code
MVM009
Programme
MVM Business Administration (MVMBUS)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
David Argyle
Current Stage
Close
Status
Closed
Start Date
28-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
17-Mar-2017
Overall Priority
Higher
Category
Discretionary

Documentation