January 2016
- Report Date
- January 2016
Achievements in Last Period
- Work on simplification of ITT by request of the project board, particularly mandatories.
- Workshops held early January with MVM staff to agree supplier demonstration scenarios.
- Business Lead requested that scenarios be expanded to include detailed checklists to allow MVM staff to agree exactly what is required to step through each evaluation; this has been agreed with Procurement, Programme Manager and Senior Supplier, but will impact on completion and approval of ITT.
- Work on ITT now planned for completion w/c 08/02/16.
Issues
- Delay to timeline due to expansion of supplier demonstration scenarios. PM assisting Business Lead to complete revised scenarios and ITT.
Next Steps
- Complete and issue ITT.
- Produce revised plan for timeline including suoplier evaluations.
- Agree contingency plans for current platform if procurement delayed.
Milestones
(to be reviewed with Project Board when ITT agreed)
| 22-Jan-2016 | Issue Invitation To Tender (ITT) |
| 04-Mar-2016 | Return of ITT |
| 08-Mar-2016 | ITT Evaluation Starts |
| 15-Apr-2016 | ITT Evaluation Phase Ends |
| 18-Apr-2016 | Award Recommendation |
| 29-Apr-2016 | Award Letter |
| 13-Jun-2016 | Contract Signed |
| 15-Jul-2016 | Closure |
- Approved budget
- 120.0 days
- Activity this month
- 12.0 days
- Activity this year
- 55.0 days
- Activity to date
- 55.0 days
- Estimate to complete current year
- 86.0 days
- Estimate to complete future years
- 0.0 days