January 2016

Report Date
January 2016

Achievements in Last Period

  • Work on simplification of ITT by request of the project board, particularly mandatories.
  • Workshops held early January with MVM staff to agree supplier demonstration scenarios.
  • Business Lead requested that scenarios be expanded to include detailed checklists to allow MVM staff to agree exactly what is required to step through each evaluation; this has been agreed with Procurement, Programme Manager and Senior Supplier, but will impact on completion and approval of ITT.
  • Work on ITT now planned for completion w/c 08/02/16.

 

Issues

  • Delay to timeline due to expansion of supplier demonstration scenarios. PM assisting Business Lead to complete revised scenarios and ITT.

 

Next Steps

  • Complete and issue ITT.
  • Produce revised plan for timeline including suoplier evaluations.
  • Agree contingency plans for current platform if procurement delayed.

 

Milestones

(to be reviewed with Project Board when ITT agreed)

22-Jan-2016Issue Invitation To Tender (ITT)
04-Mar-2016Return of ITT
08-Mar-2016ITT Evaluation Starts
15-Apr-2016ITT Evaluation Phase Ends
18-Apr-2016Award Recommendation
29-Apr-2016Award Letter
13-Jun-2016Contract Signed
15-Jul-2016Closure
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
Change Status
Activity
Approved budget
120.0 days
Activity this month
12.0 days
Activity this year
55.0 days
Activity to date
55.0 days
Estimate to complete current year
86.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Tristan Replacement - Procurement
Code
MVM009
Programme
MVM Business Administration (MVMBUS)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
David Argyle
Current Stage
Close
Status
Closed
Start Date
28-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
17-Mar-2017
Overall Priority
Higher
Category
Discretionary

Documentation