December 2016

Report Date
December 2016

Achievements in Last Period

  • Video conference sessions took place w/c 05/12/16 where Provet worked through the scenarios with Vet staff and presented the most recent changes to Provet Cloud functionality; Business Lead then carried out gap analysis for Provet to produce a revised plan for the required development for implementation focussing on Phase 1.
  • Sample data has been provided to allow Provet to provide options for migration of legacy data.
  • Contract negotiations continue.
  • Next Project Board meeting confirmed for 19/01/17.
  • Implementation project MVM509 has been initiated; milestones are dependent on completion of MVM009 specifically the signing of the contract.

 

Issues

  • No major issues; contract negotiations have taken longer than hoped however there was an understanding that completing in December was optimistic and inevitably with limited staff availability in December this has been pushed into January.

 

Next Steps

  • Review budget, resourcing, timeline and milestones.
  • Complete contract negotiations and get contract signed off by all parties.
  • Agree (procurement) project closure.

The project current status is AMBER due to delays completing contract negotiations.

 

Milestones

(NB outstanding milestones remain subject to change due to ongoing contract negotiations)

23-Jan-2017 Contract Signed
27-Jan-2017 Closure
Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
147.0 days
Activity this month
10.0 days
Activity this year
34.0 days
Activity to date
163.0 days
Estimate to complete current year
5.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Tristan Replacement - Procurement
Code
MVM009
Programme
MVM Business Administration (MVMBUS)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
David Argyle
Current Stage
Close
Status
Closed
Start Date
28-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
17-Mar-2017
Overall Priority
Higher
Category
Discretionary

Documentation