October 2016

Report Date
October 2016

Achievements in Last Period

  • Project Board met 12/10/16, and discussed outcome of discussions between Gavin McLachlan and David Argyle; David chaired the meeting and outlined options, recommending that the contract be awarded to Supplier 1; this proposal was discussed by the Project Board and supported.
  • Award recommendation report was completed w/c 24/10/16 and signed off by Procurement and the Head of School.
  • Award and reject letters were issued to Suppliers on 26/10/16 - this is a significant step forward for the project.

 

Issues

  • The delay reaching a decision and the additional effort spent on protracted discussions has resulted in more budget being used than was anticipated to reach this point; the budget needs to be addressed in discussion with the Project Board.

 

Next Steps

  • Agree revised timeline and milestones.
  • Agree project governance with Head of School.
  • Arrange meetings with successful supplier to discuss expectations of relationship with University, implementation, and contract negotiations.
  • Review risks with Project Board.
  • Review budget and resourcing.

The project current status is AMBER; due to the delay to reaching the decision and the additional effort spent getting there - despite the award of contract being agreed - this should move to GREEN next month.

 

Milestones

(NB this revised timeline is based on the letters going to suppliers 26/10/16 but is subject to change as the standstill period is not yet complete)

13-Dec-2016 Contract Signed
23-Dec-2016 Closure
Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
147.0 days
Activity this month
7.0 days
Activity this year
24.0 days
Activity to date
153.0 days
Estimate to complete current year
6.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Tristan Replacement - Procurement
Code
MVM009
Programme
MVM Business Administration (MVMBUS)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
David Argyle
Current Stage
Close
Status
Closed
Start Date
28-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
17-Mar-2017
Overall Priority
Higher
Category
Discretionary