July 2016
- Report Date
- July 2016
Achievements in Last Period
- Additional Project Board arranged for 21/07/16 to reconvene and discuss resolution of outstanding issues.
- Further clarifications received from suppliers.
- Scoring on Award system completed and commercial responses clarified and confirmed.
Issues
- Supplier 1 functionality not considered acceptable on clinical scenario (min threshold); supplier 2 timeline potentially one year later that supplier 1. These issues and commercials were discussed with Project Board 21/07/16; It was agreed that a decision could not yet be reached; further discussion to be had with Supplier 1 and 2 on clinical functionality to be and timeline respectively, and update Project Board at next scheduled meeting 10/08/16.
Next Steps
- Further discussions with suppliers under guidance of Procurement Manager.
- Prepare recommendation for Project Board.
- Review risks with Project Board.
- Review budget and resourcing.
The project current status is RED due to further delay reaching decision.
- Approved budget
- 147.0 days
- Activity this month
- 6.0 days
- Activity this year
- 129.0 days
- Activity to date
- 129.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 30.0 days