July 2016

Report Date
July 2016

Achievements in Last Period

  • Additional Project Board arranged for 21/07/16 to reconvene and discuss resolution of outstanding issues.
  • Further clarifications received from suppliers.
  • Scoring on Award system completed and commercial  responses clarified and confirmed.

 

Issues

  • Supplier 1 functionality not considered acceptable on clinical scenario (min threshold); supplier 2 timeline  potentially one year later that supplier 1. These issues and commercials were discussed with Project Board 21/07/16; It was agreed that a decision could not yet be reached; further discussion to be had with Supplier 1 and 2 on clinical functionality to be and timeline respectively, and update Project Board at next scheduled meeting 10/08/16.

 

Next Steps

  • Further discussions with suppliers under guidance of Procurement Manager.
  • Prepare recommendation for Project Board.
  • Review risks with Project Board.
  • Review budget and resourcing.

The project current status is RED due to further delay reaching decision.

Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
Change Status
Activity
Approved budget
147.0 days
Activity this month
6.0 days
Activity this year
129.0 days
Activity to date
129.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
30.0 days

Project Info

Project
Tristan Replacement - Procurement
Code
MVM009
Programme
MVM Business Administration (MVMBUS)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
David Argyle
Current Stage
Close
Status
Closed
Start Date
28-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
17-Mar-2017
Overall Priority
Higher
Category
Discretionary

Documentation