February 2016
- Report Date
- February 2016
Achievements in Last Period
The project scope was changed in Q4 2015 to include the piloting of the documents as part of UAT. However, the project sponsor has been unable to find an MVM unit with the availability to do this. Accordingly, the project will descope this, and instead have the documents checked and QA'd by the existing stakeholders who contributed to the analysis. After accpetance, and before we can close project, the project needs to put in place an on-going document review and maintanenance process.
Issues
- no medium or high risks
Next Steps
- resource Elaine again and contact stakeholders
Milestones
| 31-Mar-2016 | Single Document Set - Accepted |
| 31-Mar-2016 | Process Mapping - Checklist Accepted |
| 14-Apr-2016 | Post-Project Document Support in Place |
| 28-Apr-2016 | Closure |
- Approved budget
- 30.0 days
- Activity this month
- 0.5 days
- Activity this year
- 17.0 days
- Activity to date
- 28.0 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days