January 2016
- Report Date
- January 2016
Achievements in Last Period
- project pending action from Sponsor to find a new team to pilot the process and documents
Issues
- no medium or high risks
Next Steps
- replan with team once confirmed
Milestones
New milestones to be confirmed once the team piloting the processs and documents has confirmed their dates.
RAG Change Status is Red as the current milestones for acceptance and delivery needs to be replanned, as the project scope has changed to include a pilot of the process and documents. This is at the sponsor's request, helping to make the deliverables of highest quality. New milestones for acceptance and closure) to be confirmed once the team piloting the processs and documents has confirmed their dates. The project status will move back to Green after this.
Project has been waiting three month for this information. Project Manager will advise sponsor that we suspendi project if no pilot team is found, or descope this.
- Approved budget
- 30.0 days
- Activity this month
- 0.1 days
- Activity this year
- 16.0 days
- Activity to date
- 27.0 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days