January 2016

Report Date
January 2016

Achievements in Last Period

  • project pending action from Sponsor to find a new team to pilot the process and documents

Issues

  • no medium or high risks

Next Steps

  • replan with team once confirmed

Milestones

New milestones to be confirmed once the team piloting the processs and documents has confirmed their dates.

 

RAG Change Status is Red as the current milestones for acceptance and delivery needs to be replanned, as the project scope has changed to include a pilot of the process and documents. This is at the sponsor's request, helping to make the deliverables of highest quality. New milestones for acceptance and closure) to be confirmed once the team piloting the processs and documents has confirmed their dates. The project status will move back to Green after this.

Project has been waiting three month for this information. Project Manager will advise sponsor that we suspendi project if no pilot team is found, or descope this.

Project Status
RAG Status
Time
RED
Cost
RED
Scope
RED
Overall
RED
Change Status
Activity
Approved budget
30.0 days
Activity this month
0.1 days
Activity this year
16.0 days
Activity to date
27.0 days
Estimate to complete current year
4.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Template research administration documentation set
Code
MVM007
Programme
MVM Research (MVMRES)
Project Manager
Maurice Franceschi
Project Sponsor
Paul Clark
Current Stage
Close
Status
Closed
Start Date
05-Jun-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jul-2016
Programme Priority
3
Overall Priority
Normal
Category
Discretionary