June 2015

Report Date
June 2015

Achievements in Last Period

  • project brief completed and end of planning - done

Issues

  • no medium or high risks

Next Steps

  • complete analysis
  • QA and acceptance of Process Map

Milestones

26-Jun-2015Process Mapping - End of Analysis
03-Jul-2015Process Map - Accepted
10-Jul-2015Process Map - Documented for Future Use - Delivery
28-Aug-2015Acceptance and Delivery of Templates
11-Sep-2015Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
17.0 days
Activity this month
5.0 days
Activity this year
8.0 days
Activity to date
8.0 days
Estimate to complete current year
4.0 days
Estimate to complete future years
5.0 days

Project Info

Project
Template research administration documentation set
Code
MVM007
Programme
MVM Research (MVMRES)
Project Manager
Maurice Franceschi
Project Sponsor
Paul Clark
Current Stage
Close
Status
Closed
Start Date
05-Jun-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jul-2016
Programme Priority
3
Overall Priority
Normal
Category
Discretionary