June 2014

Report Date
June 2014

Achievements in Last Period

  • Continue with WordPress Migration - End of July now date for completion
  • A TAD for the Simple Hosting signed-off by Dev Tech
  • Simple Hosting Migration completed
  • Agreement on Support Model for Simple Hosting confirmed - Done
  • First review of the Service List to identify any services which can be hosted on the Simple Hosting i/f - Done
  • Start to develop a Pro-Forma and TAD for each of the Complex Hostings - Started

Issues

  • budget likely to be insufficient to do the work in 13/14 and 14/15 - this is why the status of the project is AMBER  

Next Steps

  • Continue and commplete with WordPress Migration
  • Wait for MVM College Review so we can confirm the next tranche of 'Simple Hostint' for 2014/15 to be migrated
  • Complete Pro-Forma 

 

Milestones  

04-Jul-201427-Jun-2014Migration of Simple HostingDeliver
25-Jul-201427-Jun-2014Migrate WordPressDeliver
22-Aug-201427-Jun-2014Migration Plan and Estimates for Complex SitesExecute
22-Aug-201427-Jun-2014Governance and Service Model for Complex Sites agreedAnalyse
13-Mar-201513-Mar-2015Migrate Complex ApplicationsDeliver
31-Mar-201531-Mar-2015ClosureClose

 

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
150.0 days
Activity this month
8.0 days
Activity this year
27.0 days
Activity to date
27.0 days
Estimate to complete current year
14.0 days
Estimate to complete future years
100.0 days

Project Info

Project
MVM LTS service transition to IS
Code
MVM002
Programme
MVM Learning and Teaching (MVMLAT)
Project Manager
Maurice Franceschi
Project Sponsor
Paul Clark
Current Stage
Close
Status
Closed
Start Date
29-Jan-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Apr-2016
Programme Priority
1
Overall Priority
Normal
Category
Discretionary