June 2014
- Report Date
- June 2014
Achievements in Last Period
- Continue with WordPress Migration - End of July now date for completion
- A TAD for the Simple Hosting signed-off by Dev Tech
- Simple Hosting Migration completed
- Agreement on Support Model for Simple Hosting confirmed - Done
- First review of the Service List to identify any services which can be hosted on the Simple Hosting i/f - Done
- Start to develop a Pro-Forma and TAD for each of the Complex Hostings - Started
Issues
- budget likely to be insufficient to do the work in 13/14 and 14/15 - this is why the status of the project is AMBER
Next Steps
- Continue and commplete with WordPress Migration
- Wait for MVM College Review so we can confirm the next tranche of 'Simple Hostint' for 2014/15 to be migrated
- Complete Pro-Forma
Milestones
04-Jul-2014 | 27-Jun-2014 | Migration of Simple Hosting | Deliver |
25-Jul-2014 | 27-Jun-2014 | Migrate WordPress | Deliver |
22-Aug-2014 | 27-Jun-2014 | Migration Plan and Estimates for Complex Sites | Execute |
22-Aug-2014 | 27-Jun-2014 | Governance and Service Model for Complex Sites agreed | Analyse |
13-Mar-2015 | 13-Mar-2015 | Migrate Complex Applications | Deliver |
31-Mar-2015 | 31-Mar-2015 | Closure | Close |
- Approved budget
- 150.0 days
- Activity this month
- 8.0 days
- Activity this year
- 27.0 days
- Activity to date
- 27.0 days
- Estimate to complete current year
- 14.0 days
- Estimate to complete future years
- 100.0 days