March 2016

Report Date
March 2016

Achievements in Last Period

  • Complete closure report and Close project - not achieved - closure report out for review and sign-off

Issues

  • no open issues
  • no medium or high risks

Next Steps

  • Complete closure report and Close project by 8th April  
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
140.0 days
Activity this month
2.0 days
Activity this year
51.0 days
Activity to date
142.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
MVM LTS service transition to IS
Code
MVM002
Programme
MVM Learning and Teaching (MVMLAT)
Project Manager
Maurice Franceschi
Project Sponsor
Paul Clark
Current Stage
Close
Status
Closed
Start Date
29-Jan-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Apr-2016
Programme Priority
1
Overall Priority
Normal
Category
Discretionary