- Report Date
- March 2016
Achievements in Last Period
- Complete closure report and Close project - not achieved - closure report out for review and sign-off
Issues
- no open issues
- no medium or high risks
Next Steps
- Complete closure report and Close project by 8th April
- Approved budget
- 140.0 days
- Activity this month
- 2.0 days
- Activity this year
- 51.0 days
- Activity to date
- 142.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days