Report for December 2019
- Report Date
- December 2019
Achievements
- Scripts and storyboarding for week 1 complete
- Dates for UoE video filming confirmed
- Media training delivered to Lead Academic
Issues and changes
- Weeks 2-4 will be flexible for learners to choose whether to participate fully or particular week(s) only.
Next steps
- Marketing meeting organised for 8 January
- Film 4 x week 1 videos, 1 x week 4 video and 1 x week 5 video
- Identify graphics requirements
- Content review meeting organised for 21 January
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days