- Report Date
- December 2019
Achievements
- Confirmation received that funding has been secured
- Initial meeting held to agree high level timeline and approach
Issues and changes
Next steps
- Organise kick-off meeting
- Organise Learning Design Workshop
- Register MOOC with edX
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days