- Report Date
- September 2019
Achievements
- Kick off meeting held 25 September
- Learning Design 80% complete
- High level timeline and milestones drafted
- 50% of key production dates agreed with academic team
- Risk Register produced
Issues and changes
Next steps
- Finalise Learning Design by mid October
- Agree remaining key production dates with all teams by mid October
- Approve high level timeline and milestones
- Hold writing workshops in October
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days