October 2019

Report Date
October 2019

Achievements

  • Learning Design 80% complete
  • Writing Retreats held with Academics
  • Content Review meeting held end October
  • Content received for weeks 1, 4 and 5 (30%)
  • Platform development underway

Issues and changes

  • Content writing not complete.  Concerted effort required to finalise all content by mid November

Next steps

  • Finalise Learning Design
  • Redo timeline factoring in proposed staff strikes Nov/Dec and revised date for completion of all content
  • Agree revised key dates with all teams
  • Commence media production early November
  • Finalise all content and script
  • Produce marketing plan

 

Project Status
RAG Status
Overall
AMBER
RAG Commentary
Content writing not complete. Concerted effort required to finalise all content by mid November
Change Status
Overall
Moderate
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Data Ethics, AI and Responsible Innovation
Code
MOOC0029
Programme
MOOC Development Projects (In Delivery)
Management Office
ISG PMO
Project Manager
Colette Maxwell
Project Sponsor
Melissa Highton
Current Stage
Execute
Status
In Progress
Project Classification
Grow
Start Date
04-Sep-2019
Planning Date
n/a
Delivery Date
n/a
Close Date
01-May-2020
Overall Priority
Normal

Documentation

Not available.