Current project status

Report Date RAG Budget Effort Completed Effort to complete
December 2019 GREEN 0.0 days 0.0 days 0.0
Content
Status
In Progress
Current Stage
Initiate
Start Date
Friday, 13 December 2019
Planning Date
Friday, 14 February 2020
Delivery Date
Friday, 28 August 2020
Close Date
Friday, 27 November 2020
Project information
Project Code
MLE008
Programme
ISG - Lecture Recording (MLE)
Session
20/21
19/20
Organisational Unit
Learning Teaching and Web
Project Management Office (if relevant)
ISG PMO
Responsibility
Learning Teaching and Web
Project Category
Discretionary
Project Classification
Grow
Project Type
Implementation
Project Size
Medium
Project Complexity
Standard
Alignment to Strategy 2030 and Adaptation & Renewal Team (ART)
Teaching and Learning
Funding Source
LTW
Programme Priority
1
Overall Priority
Normal
Student Impact
Project deliverables will be used by students
Specialist Skills
Communications
PMO Support
Training