Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for June 2019 June 2019 GREEN GREEN GREEN GREEN
Report for April 2019 April 2019 GREEN GREEN GREEN GREEN
Report for February 2019 February 2019 GREEN GREEN GREEN GREEN
Report for December 2018 December 2018 GREEN GREEN GREEN GREEN
Report for October 2018 October 2018 GREEN GREEN GREEN GREEN

Project Info

Project
Playful Strategy Phase 2
Code
LTW008
Programme
Innovation Programme 2018/19
Management Office
ISG PMO
Project Manager
Charlie Farley
Project Sponsor
Melissa Highton
Current Stage
Close
Status
Closed
Start Date
29-Oct-2018
Planning Date
n/a
Delivery Date
n/a
Close Date
26-Jul-2019
Overall Priority
Normal