Report for July 2017
- Report Date
- July 2017
Achievements in Last Period
- Alma workflow fix provided to Sandbox on 23rd July and will be released on 6th Aug
- Handover to supplier support completed
- Final Project Board prep and meeting held on 27th July, handover to Service Board which will meet twice a year
- Project Closure and Lessons Learned drafted and issued out for review and sign off
Issues
- Recommendations for automated course code data to be reviewed with Programme Manager for a new project next financial year
- Any unspent budget (8 days) will be transferred on closure to ISG Portfolio
- Extension of Talis contract to cover resits until 19th August - this was funded by L&UC
Next Steps
- Closure approval
The project status is GREEN
| 04-Aug-17 | Closure |
- Approved budget
- 100.0 days
- Activity this month
- 1.2 days
- Activity this year
- 90.3 days
- Activity to date
- 92.3 days
- Estimate to complete current year
- 0.1 days
- Estimate to complete future years
- 0.0 days